PERFORMING METHOD TALK SHOP CERAMICAL FLOOR
A. PLANNING
I. SHOP DRAWING:
- DETERMINING CERAMICAL CUT REST HAS > ½ CERAMICAL BODY.
- DETERMINING CERAMICAL NAD WALL & THAT FLOOR MEETS & NAD UNIFORM DELFT.
- DETERMINE SO DELFT CROSSROAD MEETS.
- DETERMINING SANITAIR'S LAYOUT & FIXTURE : SHALL AT CROSSROAD / CERAMICAL BODY MEAN.
- DETERMINING CERAMICAL ASSEMBLY STARTING POINT.
- DETERMINING MINIMAL EXPANTION JOINT EACH 12 M² 16 M².
II. RESOURCES'S COUNT( RESOURCE) :
a. MATERIAL THAT IS UTILIZED:
- DELFT.
- PC CEMENT.
- WATER.
- ADDITIVE.
b. TOOL THAT IS UTILIZED:
- ALUMINIUM MARGIN.
- WATER TUB( PAIL).
- DUDUKAN / TATAKAN'S PLACE DELFT.
- YARN OR STRING.
- RUBBER MALLET.
- SPESI'S SPOON.
- WATERPASS.
- SPADE.
- SPUME / SPONGE
- CLOTH / WET MOP.
c. LABOUR: DETERMINING NEEDED LABOUR ON SCHEDULE AND WORK VOLUME.
CERAMICAL SOAKING THAT WILL BE ASSEMBLED INTO WATER TUB( PAIL) UP TO 1 HOUR.
EXAMPLE: WATER TUB